Work in March
2nd Floor Math Classrooms
- Began & Completed Selective Demolition of walls, ceilings, and flooring.
- Began Installing new wall framing, ductwork, and electrical.
- Demolished two exterior walls in preparation for two new full-height windows.
1st and 2nd Floor Bathrooms
- Began selective demolition of walls, floors, and ceilings in preparation for brand new restroom refresh.
Exterior Work
- Lifted two new Trane building chillers to rooftop.
- Made final piping and power connections to new Trane building chillers.
Upcoming Work in April
2nd Floor Math Classrooms
- Install structural steel at two new window openings
- Install new HVAC unit (AHU-39) to serve new math classrooms
- Install drywall on new walls
1st and 2nd Floor Bathrooms new auditorium
- Sawcut, remove existing floor on 1st floor
- Install new underground plumbing
- Pour concrete for new floor
Exterior Work
- Start-up and commission new building cooling system
Progress Photos
Safety
- Lost Time Days: 0
Project Team
Kraus-Anderson Construction Company
Dustin Kempf, Senior Project Manager
Dave Brust, Project Superintendent
Jesus Espinoza, Assistant Superintendent
Brennan Burrows, Project Manager
Shanna Haney, Lead Project Coordinator