What is happening?
Work in Progress/Work Starting This Week
- Storm shelter addition: Pouring the slab on grade this week
- Interior Bathrooms: toilet fixture installtions to start this week
- Kitchen: quarry tile patch work at new fixtures and equipment to start this week
- Sitework: misc signage work on-going
- Media Center: flooring work on-going
Work Starting Soon
- Storm Shelter addition: air barrier and brick installation on the exterior to start week of 8/15/22
- Interior Bathrooms: Doors and Hardware installations will follow toilet fixture installations
- Kitchen: kitchen equipment installations to start next week
- Site Work: final lift of asphalt 8/17/22
- Media Center: Ceilings to be padded out next week
Work Completed Recently
- Storm Shelter addition – Roofing over the new addition will be completed this week
- Interior Bathrooms: tile work in all (6) bathrooms to be wrapped up
- Kitchen: coolers & freezers were installed and completed this week
- Sitework: 1st lift of asphalt and also site concrete completed this week
- Media center: all drywall and painting work complete
Fun Facts
Fun Fact #1: This is one of the first storm shelters completed recently with poured concrete walls up to deck
Fun Fact #2: Our Slab on grade for the storm shelter is almost 9” thick, significantly thicker than any typical concrete floor
Photos
Kraus-Anderson
Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com
Andy Thompson, Project Manager | andy.thompson@krausanderson.com
Wold Architects
Nick Thompson, Associate | nthompson@woldae.com
Kyle Hoverson, Associate | khoverson@woldae.com