Otter Lake Elementary School

What is happening?

Work in Progress/Work Starting This Week

  • Storm shelter addition: Pouring the slab on grade this week
  • Interior Bathrooms: toilet fixture installtions to start this week
  • Kitchen: quarry tile patch work at new fixtures and equipment to start this week
  • Sitework: misc signage work on-going
  • Media Center: flooring work on-going

Work Starting Soon

  • Storm Shelter addition: air barrier and brick installation on the exterior to start week of 8/15/22
  • Interior Bathrooms: Doors and Hardware installations will follow toilet fixture installations
  • Kitchen: kitchen equipment installations to start next week
  • Site Work: final lift of asphalt 8/17/22
  • Media Center: Ceilings to be padded out next week

Work Completed Recently

  • Storm Shelter addition – Roofing over the new addition will be completed this week
  • Interior Bathrooms: tile work in all (6) bathrooms to be wrapped up
  • Kitchen: coolers & freezers were installed and completed this week
  • Sitework: 1st lift of asphalt and also site concrete completed this week
  • Media center: all drywall and painting work complete

Fun Facts

Fun Fact #1: This is one of the first storm shelters completed recently with poured concrete walls up to deck

Fun Fact #2: Our Slab on grade for the storm shelter is almost 9” thick, significantly thicker than any typical concrete floor

Photos

Kraus-Anderson

Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com

Andy Thompson, Project Manager | andy.thompson@krausanderson.com

Wold Architects

Nick Thompson, Associate | nthompson@woldae.com

Kyle Hoverson, Associate | khoverson@woldae.com