What was once called the Columbus project has been officially renamed River Road Townhomes. The land disturbance permit has been issued and we are set to close on the Property 12/15/22. Site work by the adjacent Property Owner has commenced. The site is being cleared, the majority of silt fence is in place, and the temporary stream crossing has been installed. The site should be mass graded and turned over to our Site Contractor by March 1st.

We received the first round of pricing from our Site Contractor and we are below the budgeted amount so far. Furthermore, we have found additional savings that may bring that price down further.

Design Options

Progress Images

Progress Photos

Past Updates

Want to compare this month's progress with those in the past? Previous Project Updates are here for your convenience:

October 2022

For more information contact: Rob Fuller at (707) 365-6891