Willow Lane Elementary School Construction Updates

What is happening?

  • A new 1,000 SF addition to the existing media center and interior remodel of bathrooms, storage spaces, and freezer

Schedule

  • Start Date - 10/19/2020
  • Estimated Completion Date - 08/16/2021

Weekly Updates

Work Completed

  • Casework has been delivered

Work in Progress

  • Insulating piping and ductwork on-going
  • Wall blocking for Meisinger on-going in the media center
  • M&E rough-ins to be wrapped up 6/11/21

Work Upcoming

  • Casework installs
  • Install dust barrier in the corridor
  • Cut new openings into the corridor
  • Frame soffits
  • Re-pipe sprinkler
Casework delivered on site
Exterior closeup of metal panel complete
Interior wall framing and rough-ins
Willow exterior view windows & metal panels

Drone Video

Kraus-Anderson

Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com

Andy Thompson, Project Manager | andy.thompson@krausanderson.com

Jake Walton, Project Superintendent | jake.walton@krausanderson.com

Wold Architects

Shannon Hanson, Designer | shanson@woldae.com