What is happening?
- A new 1,000 SF addition to the existing media center and interior remodel of bathrooms, storage spaces, and freezer
Schedule
- Start Date - 10/19/2020
- Estimated Completion Date - 08/16/2021
Weekly Updates
Work Completed
- Casework has been delivered
Work in Progress
- Insulating piping and ductwork on-going
- Wall blocking for Meisinger on-going in the media center
- M&E rough-ins to be wrapped up 6/11/21
Work Upcoming
- Casework installs
- Install dust barrier in the corridor
- Cut new openings into the corridor
- Frame soffits
- Re-pipe sprinkler
Drone Video
Kraus-Anderson
Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com
Andy Thompson, Project Manager | andy.thompson@krausanderson.com
Jake Walton, Project Superintendent | jake.walton@krausanderson.com
Wold Architects
Shannon Hanson, Designer | shanson@woldae.com