Oneka Elementary School

What is happening?

  • Exterior Siding at penthouse
  • Exterior Brick Veneer
  • Interior Painting
  • Mechanical Pads Placement

Schedule Occurring in June

  • Storm Window install
  • Nana Wall install
  • Tile
  • Ceiling Grid
  • Casework install
  • MEP Finishes

Work Completed Last Month

  • Media Center Demo
  • Interior Drywall and taping complete
  • Storm doors installed

Kraus-Anderson