Saddlehorn Ranch April 2022

And Then There Were Six Homes

Two builders are now currently working on six homes in Phase 1. Hi-Point Home Builders have completed the trusses and roofing on the model home. Framing is underway for four Black Oak Homes and they have excavated and poured some foundation for a fifth home. Black Oak Homes pulled the permit for a sixth home, so construction will start soon, and are in the process of acquiring permits for five additional homes this week. All five Black Oak homes and the Hi-Point model home are featured in the construction update video below

At the water treatment plant, the starter rings have been installed along with the underground electric and plumbing for the building. They will be pouring the concrete slab for the water building this week. Next week, they will get the permit for the water building and are tying in the rebar for the water tank. Additionally, they are starting to cut in roads for phase two and mailboxes have been installed for Phase 1 and 2.

Saddlehorn Ranch Construction Update Video

Updated Views of Hi-Point Home Builders' Model

Black Oak Homes Continue On Track

Lot 4 framing underway. (Click a picture for a close up view.)
Lot 4 framing underway. (Click a picture for a close up view.)
Lot 7 framing underway. (Click a picture for a close up view.)
Lot 7 framing underway. (Click a picture for a close up view.)
Lot 24 framing underway. (Click a picture for a close up view.)
Lot 24 framing underway. (Click a picture for a close up view.)
Lot 24 framing underway. (Click a picture for a close up view.)
Lot 11 framing underway. (Click a picture for a close up view.)
Lot 25: we got the permit this last month so excavation was completed and foundation work is underway. (Click a picture for a close up view.)

Water Treatment Facility Progress

Water treatment facility progressing well with installed starter rings, underground electric, and underground plumbing. (Click a picture for a close up view.)

Lot Division Plan

Interactive Photos

As in other editions of this newsletter, we have prepared a series of intereactive photos for you to get a close-up look at the development's progress. These are 360-degree panorama photos shot with a drone. They allow you to click and drag to move around the image. you can also zoom in and out with your mouse or your fingers if you are using your phone. Simply click the button below to view these photos.

(Tip: If you click the white target shapes in the interactive photos, you'll move to different points around the project to get a detailed look at every part of the project. By looking up in the first photo you will see links to interactive photos from other months.)

Additional Photos

Mailboxes installed and phase 2 roads being cut. (Click a picture for a close up view.)
Aerial view of Phase 1. Lot 21 and lot 11 are visible as is the foundation of the water tank in the lower left. The red gravel on Truchas Train and Zaragoza Trail is also visible.

For more information contact: Rob Fuller at (707) 365-6891 or saddlehorn@roipropertygroup.com