Loading

Tara Creek April 2022

Construction Begins

The Land Disturbance Permit was granted on 4/19/22 and construction commenced on 4/20/22. The boundary, silt fence, retention ponds, and tree save areas have been staked with the silt fence and boundary fence installed. The silt fence and pond areas have been cleared of vegetation and pond #1 is being excavated. The demolition of Asphalt and Paving is underway.

Looking ahead, the construction entrance is to be installed on 4/29, pond #2 is to be excavated on 5/1, and the Seven Day Engineers inspection is scheduled for 5/3.

Progress Images

Past Updates

Want to look back? In the future, previous project updates will be here for your convenience.

For more information contact: Rob Fuller at (707) 365-6891