Vadnais Heights Elementary School Construction Updates

What is happening?

  • A new 400 SF maintenance addition and renovations to the kitchen, restrooms, and learning commons.

Schedule

  • Start Date - 2/1/2021
  • Estimated Completion Date - 8/20/2021

Work Completed

  • Substantial completion has been achieved.
  • Staff and student occupancy has been approved.
  • Lockers have been installed.
Learning Commons
Boys and Girls Restrooms
Kitchen
Large Group Room

Weekly updates

Work In Progress

  • Punch list work is continuing.
  • Test and balance of the mechanical system is continuing.
  • Commissioning is continuing.

Upcoming Work

  • Interior aluminum door and sliding glass installation is expected on October 21, 2021.

milestones

Interior Aluminum Door and Sliding Glass Door Installation

  • Estimated Start Date - 10/21/2021

Kraus-Anderson

Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com

Rob Gemelke, Project Manager | rob.gemelke@krausanderson.com

David Route, Project Superintendent | david.route@krausanderson.com

Wold Architects

Kyle Hoverson, Designer | khoverson@woldae.com