Transportation Facility Construction Updates

What is happening?

  • A new 12,900 SF precast transportation facility with brick clad steel-framed offices will be utilized to house, maintain, and manage the White Bear Lake Area School District vehicles and staff.

Schedule

  • Start Date - 11/16/2020
  • Completion Date - 7/23/2021

Weekly Updates

Work Completed

  • The certificate of occupancy has been obtained and the building is occupied.
  • The bus parking lot operators have been installed.
  • Test and balance of the mechanical systems is complete.

Work in Progress

  • The interior punch list work is nearly complete.
  • Exterior punch list work is nearly complete.

Upcoming Work

  • Installation of permanent overhead doors and operators is scheduled for September 17, 2021.
  • Installation of the trash enclosure gate is scheduled for September 27, 2021.

Drone Video / Images

Kraus-Anderson

Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com

Rob Gemelke, Project Manager | rob.gemelke@krausanderson.com

Brad Kloos, Project Superintendent | brad.kloos@krausanderson.com

Wold Architects

Haley Koesters, Architect | hkoesters@woldae.com