What is happening?
- Add freezer, specialist room, extended day office, and EL room
- Update classrooms and media center, safety/security upgrades
Construction Schedule
- Start Date - 11/23/2020
- Estimated Completion Date - 08/31/2021
Weekly Updates
Work in Progress
- Punchlist items will be completed when students are not in the building. These items include paint touch-up, caulking installation, casework shelf and door adjustments, mechanical commissioning, and door/hardware adjustments.
Work Completed
- Tile installation was completed at the learning commons shelving, flex space sills, and the flex space entrance doors.
- Flooring installation was completed in the learning commons flex area.
- Casework installation was completed. There are adjustments needed to the casework hardware throughout all areas.
- The trim pieces for the walk-in cooler/freezer were installed and caulked.
- Wallcovering was installed in the flex area at the new classroom addition.
Drone video
MILESTONE dates
Mobilize to the Site
- 11/23/2020
Classroom Addition
- Substantial Completion Date – 7/27/2021
Media Center
- Start Date – 6/14/2021
- Estimated Completion Date - 8/31/2021
Office Remodel
- Start Date – 6/14/2021
- Estimated Completion Date – 7/21/2021
Restroom Remodels
- Start Date – 6/14/2021
- Estimated Completion Date - 8/31/2021
Kraus-Anderson
Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com
Mark Oelrich, Project Manager | mark.oelrich@krausanderson.com
Rich Putnam, Project Superintendent | rich.putnam@krausanderson.com
Wold Architects
Jena Boldt, Designer | jboldt@woldae.com