  • Construction of a 2-Story, 68,000 square foot hospital
  • Remodel of the existing 17,000 square foot clinic
  • Construction of a 4,000 square foot maintenance building
  • Demolition of the existing hospital

Schedule

  • Construction Start – March 2022
  • Clinic Remodel – September 2022 - June 2023
  • Maintenance Building Construction – March 2023 - June 2023
  • New Hospital Completion – June 2023
  • Existing Hospital Demolition – September 2023 - October 2023
  • Construction Completion – November 2023

May 2023 Update

Work Completed

  • Installed Level 2 toilet and bath accessories
  • Installed Level 2 plumbing fixtures
  • Installed Level 1 ceiling grid
  • Installed Level 1 tile
  • Installed Level 1 wall protection
  • Installed Level 1 casework
  • Installed Level 1 doors and hardware
  • Painted clinic walls and frames
  • Installed clinic casework
  • Started up MEP equipment
  • Installed generator
  • Installed propane tanks
  • Installed Maintenance Building exterior enclosure
  • Installed Maintenance Building underground MEP rough-ins

Work Ongoing

  • Final cleaning Level 2
  • Installed Level 1 flooring
  • Installing Level 1 ceiling tiles
  • Installing interior glass
  • Testing and balancing MEP systems
  • Installing kitchen equipment
  • Installing clinic flooring
  • Installing exterior stone veneer
  • Installing exterior metal panel
  • Pouring site concrete, sidewalk, and curb
  • Pouring Maintenance Building slab

Work Upcoming

  • Final clean Level 1
  • Installing Level 1 flooring
  • Install Maintenance Building interior walls
  • Demo existing Clinic brick and siding
  • Install Clinic siding
  • Install asphalt pavement
  • Install landscaping
  • Install bulk oxygen tank

DRONE VIDEO

INTERIOR PHOTOS

DRONE PHOTOS

Rachael Oelke, Senior Project Manager

Weston Gumbert, Assistant Project Manager

Jon Bush, Lead Superintendent

Dave Brust, Project Superintendent

Debbie Johnson, Project Coordinator

Sigita Zayden, Project Accountant

Vince La Barbera, Director of Healthcare

Mike McGraw, Director of Construction Administration

Tommy Schneider, Project Manager

Jane Foran, Project Coordinator

Cindy Gall, Interior Designer

April Guenther, Interior Designer

Bailey Nelson, Aerial Photographer