North Star Elementary Construction Updates

What is happening?

  • New elementary school for 720 students (new site)

Schedule

  • Start Date - April 2021
  • Estimated Completion Date - Fall 2022

Work Started

  • WD-2 Install has begun

Work Starting Next Week (7/31/2022)

  • Final paving and striping

Work in Progress

  • WD-2 panel install
  • Intersection retention pond rework
  • Punch list

Work Completed

  • Heating and cooling system complete and ready to run
  • Gym flooring
  • Intersection traffic light on and operating
  • Furniture move in (owner)
  • Playground installed (Pictured)
Boilers installed and ready to run
Pumps installed and ready to run
Gym floor complete
Intersection traffic light on
Furniture moved in

Drone Video / Images

July 21, 2022
June 14, 2022
April 27, 2022
March 16, 2022
February 16, 2022
January 3, 2022
November 22, 2021
11.01.2021

360 Degree images

Kraus-Anderson

Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com

Kent Henry, Project Manager | kent.henry@krausanderson.com

Terry Coleman, Project Superintendent | terry.coleman@krausanderson.com

Wold Architects

Kyle Hoverson, Associate | khoverson@woldae.com

Tyler Ertl, Architect | tertl@woldae.com