What is happening?
Work in progress or work starting this week
- Flooring in the new flex space addition and also the media center will be completed this week
- Bathroom tile will be wrapped up by the end of this week (8/12/22)
- Bathroom fixtures will be installed this week
- Remaining casework to be installed this week for media center and interior spaces
Work starting soon
- Waterproofing work at main entrance to start 8/15/22
- Ceilings to be padded out completely week of 8/15/22
- Painting touch up work to start
- Punch List August 16th
- Final cleaners week of 8/15 and 8/22 as needed
Work completed recently
- Casework in the new addition
- Nanawall install in the new addition
- Lighting in the new addition
- MEP work in the new addition
- Exterior asphalt and landscape work
Fun Facts
Fun Fact #1: We have been able to work on the new addition since early Fall of 2021, while school is in session with little to no disruptions of daily school functions
Fun Fact #2: We have less than 50SF of terrazzo patch on this job, but it still took 4 total samples/ mix designs to achieve the ideal match
Photos
Kraus-Anderson
Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com
Andy Thompson, Project Manager | andy.thompson@krausanderson.com
Wold Architects
Nick Thompson, Associate | nthompson@woldae.com
Kyle Hoverson, Associate | khoverson@woldae.com