Birch Lake Elementary School

What is happening?

Work in progress or work starting this week

  • Flooring in the new flex space addition and also the media center will be completed this week
  • Bathroom tile will be wrapped up by the end of this week (8/12/22)
  • Bathroom fixtures will be installed this week
  • Remaining casework to be installed this week for media center and interior spaces

Work starting soon

  • Waterproofing work at main entrance to start 8/15/22
  • Ceilings to be padded out completely week of 8/15/22
  • Painting touch up work to start
  • Punch List August 16th
  • Final cleaners week of 8/15 and 8/22 as needed

Work completed recently

  • Casework in the new addition
  • Nanawall install in the new addition
  • Lighting in the new addition
  • MEP work in the new addition
  • Exterior asphalt and landscape work

Fun Facts

Fun Fact #1: We have been able to work on the new addition since early Fall of 2021, while school is in session with little to no disruptions of daily school functions

Fun Fact #2: We have less than 50SF of terrazzo patch on this job, but it still took 4 total samples/ mix designs to achieve the ideal match

Photos

Exterior view of new addition with asphalt and markings work complete
View of interior flex space addition with casework and Nanawall complete, flooring on-going
Interior flex space addition with storefront complete and flooring on-going
Interior media center view showing ceiling, lighting and flooring near completion
Similar interior view of media center, break out spaces, and view into the cafeteria

Kraus-Anderson

Jason Peterson, Senior Project Manager | jason.peterson@krausanderson.com

Andy Thompson, Project Manager | andy.thompson@krausanderson.com

Wold Architects

Nick Thompson, Associate | nthompson@woldae.com

Kyle Hoverson, Associate | khoverson@woldae.com