Memorial Hospital of Lafayette County New Hospital & Clinic - Darlington, WI

What is Happening?

  • Construction of a 81,000 square foot hospital & clinic

Schedule

  • Open Air Open House - September 18, 2022
  • Core & Shell Drawing Set Release For Bidding – December 2022
  • Enclosure & Interior Drawing Set Release For Bidding – March 2023
  • Construction Start – March 2023

August 2022 Update

Work Completed

  • Schematic Design Estimate

Work Ongoing

  • Finalize Building Design
  • Finalize Site Design
  • Individual Room Layout Planning
  • Finishes Planning

Work Upcoming

  • Design Development Document Completion
  • Design Development Estimate
MHLC staff thanking Senator Baldwin for $4Million in Congressional Directed Spending for our replacement hospital

Megan Geiser, Project Manager

Megan.geiser@krausanderson.com

John Ford, Senior Design Architect

Jesse Duff, Project Manager

Scott Hole, Project Manager