BCSD Capital Project Summer 2022 Progress UpdateSummer 2022 Progress Photos
New windowsills in classrooms 110, 112, the business office 119, and the faculty room B120A are also being installed. Window caulk asbestos removal from classrooms 113-115, 118B and 118C has been completed, and windows in classrooms 107-118C are being replaced.
BMHS Cafeteria kitchen new walk-in coolers/freezers, dishwasher, and durable flooring will be installed. Along with trenching work for new plumbing.
Front steps replaced and additional handrails will be added. There will also be landscaping work done in front of the building.
Berlin Middle High School Science classrooms 125, 126, and 127 will also see major updates with floor trenching, installing and replacing of electrical and plumbing, unit ventilators, countertops, and flooring.
BMHS Main Office has been gutted and will be completely renovated.
BMHS Main Office has been gutted and will be completely renovated.