Three-story, 317,000 SF high school, which will accommodate 1,600 students, contains new classrooms, state-of-the-art industrial arts labs and shop spaces, and an 825-seat auditorium, gymnasium, and a large commons/cafeteria space in the center of the building. The new high school will be located on a 90-acre site with parking lots for 890 vehicles. The project also includes a five-station field house with walking track, a 3,451-seat football stadium, eight tennis courts, four soccer/lacrosse fields, two softball fields, two baseball fields, and a synthetic turf field and full track at the stadium.
Construction is expected to be completed in the summer of 2023.
MONTHLY UPDATES
SITE CONSTRUCTION
Work Started
- Synthetic turf field stone base
- Parking lot light pole bases
- Stadium fencing
Work in Progress
- Varsity dugout masonry
- Athletic field irrigation
- Site concrete throughout athletic fields
- Site fencing
- Underground electrical rough-ins at stadium
- Site utilities (drain tile)
Work Completed
- Installed aglime at ball fields
- Baseball field concrete
- Drain tile for multi-purpose field
Work Upcoming Next Month
- Asphalt paving for paths through athletic fields
- Fencing around tennis courts
- Start paving parking lots
3-STORY CLASSROOM
Work Started
- 3rd floor drywall
- Exterior window installation (pictured)
Work in Progress
- Exterior face brick
- Roof drain piping
- 3rd floor mechanical and electrical rough-ins
- 2nd floor framing
- 2nd floor mechanical and electrical rough
Work Completed
- First floor underground electrical and plumbing rough-ins
- 3rd floor in wall backing
- Concrete slab on grade install
Work Upcoming Next Month
- Start painting 3rd floor
- Start tile on 3rd floor
- Start ceilings on third floor
- Drywall on 2nd floor
- Start exterior metal panel installation
- 1st floor fireproofing
ATHLETIC / ACTIVITIES SPACES
Work Started
- Exterior framing for fitness center (pictured)
- Plumbing rough-ins in locker rooms
- Interior masonry walls in locker rooms
- Auxiliary gym MEP Rough-ins
- Painting auxiliary gym
Work in Progress
- Main gym walking track steel
- Underground electrical rough-ins throughout gymnasium
Work Completed
- Structural steel for fitness center
- Set chillers for building
- Auxiliary gym walking track
- Auxiliary gym slab on grade
Work Upcoming Next Month
- Wrestling room roofing
- Pour main gym walking track slab
- Prep main gym for concrete slab
COMMONS / CAFETERIA
Work Started
- Commons interior framing
- Kitchen and mechanical room interior masonry
Work in Progress
- Intumescent fireproofing on exposed steel
Work Completed
- Underground electrical rough-ins
- Poured kitchen slabs
- Poured main mechanical room slab
- Completed commons roofing
Work Upcoming Next Month
- Set main mechanical room equipment
- Continue interior framing
- Set walk-in cooler/freezer
AUDITORIUM/MUSIC SPACES
Work Started
- Roofing of music rooms
Work in Progress
- Underground electrical rough-ins
Work Completed
- Underground plumbing in music rooms
- Structural steel for music classrooms
- Exterior framing
- CMU masonry in the auditorium
- Roofing of auditorium
Work Upcoming Next Month
- Install smoke hatches for auditorium
- Start pouring auditorium stepped seating
- Start pouring music room slabs
DRONE FOOTAGE & IMAGES
TIMELAPSE VIDEO
RENDERINGS
PROJECT PHOTOS
Kraus-Anderson
Jason Rentmeester, Senior Project Manager | jason.rentmeester@krausanderson.com
Michael Stenbeck, Project Manager | michael.stenbeck@krausanderson.com
Dan May, Project Manager | dan.may@krausanderson.com
Rob Gemelke, Project Manager | rob.gemelke@krausanderson.com
Randy Haram, Project Superintendent | randy.haram@krausanderson.com
Wold Architects and Engineers
Ben Beery, Associate | bbeery@woldae.com
Paul Aplikowski, Partner | paplikowski@woldae.com