Covington Creek 2 July 2023

Progress Update

The mass grading is complete. The installation of retaining walls and storm has begun. We found a lot of Rock on phase 2 but have changed the design of the site to avoid the majority of it while not losing any lots. The progress video below starts with showing phase 1 and switches to phase 2 at :12 seconds.

Progress Video

Progress Photos

Aerial Images
Ground Images