Horizontal Headway
Mass Grading is 70% complete and storm installation is underway. The majority of the concrete storm water structures have been delivered to the site and are being installed. Additionally, the building pads are being graded and put on finished floor elevations.
We are waiting on PVC and Ductile Iron Pipes for the Sewer and Water installation and are contacting the municipality to see if we can substitute PVC for Ductile throughout as PVC will arrive much sooner. We met with the electricity provider on site 6/24/22 and agreed upon a layout for all street crossings and transformers. We are waiting on their design. We have also obtained our first round of vertical construction pricing and are meeting with the general contractor on 6/30/22 to discuss the pricing and look for Value Engineering opportunities.