Project Update
This month, we've ordered pipe for all the utilities and are now preparing to start laying the water utilities, including the storm and sewer line. We also have created the full site map.
Progress Photos
Design Options
Past Updates
Want to compare this month's progress with those in the past? Previous Project Updates are here for your convenience:
October 2022 - November 2022 - December 2022 - January 2023 - February 2023 - March 2023