Leasing is Live
Framing is complete and windows are installed for the first 15 buildings. The first 5 buildings are fully dried in with roof shingles. Buildings 16-19 are in vertical construction. Slabs are poured for building 19. Water is connected to the city. The leasing website has been launched and the street side sign has been installed.