Lee Land Farms June 2023

Progress Update

We have completed all the precon meetings with City, county, utilities, and site contractor. We will be mobilizing July 17th to begin site clearing. Mass grading will begin in August. It's a 22 acre site so that will take approximately 6 weeks to grade. Then we start the stormwater middle September. Curbing and binder is scheduled November/December. There are no new Site or Design images.