Progress Update
We have completed all the precon meetings with City, county, utilities, and site contractor. We will be mobilizing July 17th to begin site clearing. Mass grading will begin in August. It's a 22 acre site so that will take approximately 6 weeks to grade. Then we start the stormwater middle September. Curbing and binder is scheduled November/December. There are no new Site or Design images.
Site Photos
Design Images
Past Updates
Want to look back? Previous project updates are here for your convenience:
May 2022 - July 2022 - August 2022 - September 2022 - October 2022 - November 2022 - December 2022 - January 2023 - March 2023 - April 2023 - May 2023
For more information contact: Rob Fuller at (707) 365-6891