Sewer Installation
We received floor plans back from our architect. The sewer lift station received an important permit that allows us to cross over an existing utility easement with our new sewer line. We began installing the sewer on site. We’ve coordinated a connection between the local utility company and an international transformer manufacturer which allows us to purchase transformers that have shorter lead time. We have also found a great discount on electrical panels that has helped us reduce costs.
Construction Update Videos
Progress Images
Design
Past Updates
Want to compare this month's progress with those in the past? Previous Project Updates are here for your convenience:
August 2022 September 2022 October 2022 November 2022 December 2022
For more information contact: Rob Fuller at (707) 365-6891