Cecile Ct December 2022

And Then There Were Two

Lot 2 is still progressing well. For lot 5, we are starting to prep for interior paint. most cabinets are in with the doors and drawers ordered. Striping is done on the street (ie stop signs and yellow lines) and we are waiting on tamper-proof hardware for the street signs. Lot 5 is projected to be completed in February.