Tara Creek November 2022

Preparing for Permits

Work in the Right of Way is underway, the sewer tap has been made, and they acceleration lanes and deceleration lanes are under construction. The sewer installation is ~100% complete and passed a pressure test as well as the Camera review. These test results have been provided to Clayton County Sewer Authority. Curb and Gutter are 90% installed. The power layout and design are incorporated into the site layout and have started fiber on their layout and design.

We are finalizing the MEP design and will submit the building permits for the first two buildings the first week of December with the hope of pouring slabs for the first three buildings once the Vertical financing is in place.

Progress Images

Aerial Photos

Past Updates

Want to look back? Previous project updates will are here for your convenience.

April 2022 May 2022 June 2022 July 2022 August 2022 September 2022 October 2022

For more information contact: Rob Fuller at (707) 365-6891