Phase 2 Has Officially Begun
There have been some delays with completing the water systems while we conduct some extra testing to ensure proper operation. We are waiting for the main control panel for the filtration system to finish testing and expect it to be delivered in December for installation. We are moving our drone video updates to quarterly instead of monthly.
For phase 1, once installation is complete for the water filtration system, we can move forward with testing for certification. We will then be able to get certificates of occupancy for the homes that are built. Vertical construction continues to move forward.
For phase 2, we have started cutting in the roadway and will be done laying water lines by mid-December. We expect dry utility installation to start Q1 of 2023.
Phase 1 Water Facility
Phase 1 Vertical
Phase 2 Horizontal
Other Progress
Lot Division Plan
Interactive Photos
We have prepared a series of interactive photos for you to get a close-up look at the progress. These are 360-degree panorama photos shot with a drone. They allow you to click and drag to move around the image. you can also zoom in and out with your mouse (or your fingers if you are using your phone). Simply click the buttons below to view these photos.
(Tip: If you click the white target shapes in the interactive photos, you'll move to different points around the project. By looking up in the first photo you will see links to interactive photos from other months.)
Past Updates
April 2022 May 2022 June 2022 July 2022 August 2022 September 2022 October 2022
Visit the Saddlehorn Website here.
For more information contact: Rob Fuller at (707) 365-6891 or saddlehorn@roipropertygroup.com