Loading

Tara Creek March 2023

Ready for Vertical

This month, we submitted plans for all of the homes and are now awaiting approval so we can begin construction on the vertical build. All the curbs and gutters are now installed, as well as the base road, so we are ready to start vertical construction as soon as the city permits.

Additionally, the “Bio-swales” are complete and have passed inspection. The “As-Built” survey is underway and will be submitted to Clayton County in early March. Upon approval, we can submit the Building Permits for review.

The contract is signed and the Building Permits are submitted for Buildings 1, 2 and 9. Plans for buildings 3 through 6 will be ready for submittal on 5/1/23.

Progress Images

Past Updates

Want to look back? Previous project updates will are here for your convenience.

April 2022 - May 2022 - June 2022 - July 2022 - August 2022 - September 2022 - October 2022 - November 2022 - December 2022 - January 2023 - February 2023

For more information contact: Rob Fuller at (707) 365-6891

Credits:

Aerial Innovations